Summary Time Line

Month 1
05/11/13 - Toured the model home.
05/12/13 - Put deposit (refundable) down on lot of $500
05/13/13 - Pre-approval from NVR.
05/15/13 - Signed Purchase agreement and paid $2500 down payment.
05/20/13 - Lender meeting/signed loan documents

Month 2
06/01/13 - Guardian Appointment
06/07/13 - Advanced Flooring Appointment
06/17/13 - Final Selections Meeting
06/24/13 - Broke Ground (Progressive pictures begin "count" of Week 1)
06/28/13 - Pre-Construction Meeting with PM(s)

Month 3
07/13/13 - Slab poured (darn rain delay)
07/19/13 - Framing Started
07/26/13 - Framing complete including a roof!

Month 4
08/05/13 - Pre-dry wall walk through and shingles installed
08/17/13 - Siding complete and insulation.
08/24/13 - Dry wall complete
08/31/13 - Cabinets installed, molding, doors and tile hung, outside trim finished including gutters.

Month 5
09/07/13 - Laminate flooring, lighting, appliances, granite, remaining hardware on doors.
09/15/13 - Landscaping, installation of window screens, paint touch ups, caulk molding
09/20/13 - Carpet was installed.  Front door painted.  Occupancy Permit Issued.
09/27/13 - Exterior Power Washed.  Interior checked one last time for any touch-ups.

Month 6
10/04/13 - Interior Cleaned
10/11/13 - Final Walk-through scheduled 10/10/13
10/18/13 - Scheduled Close date 10/15/13